• BRIDGEWATER POINT •

• LATEST UPDATE •

APRIL 2018.

The show unit is now complete.


• COMPLETION DUE Q1 2018 •

Next panel

Next panel

Next panel

• ADELPHI WHARF PHASE 1 •

• LATEST UPDATE •

APRIL 2018.

All kitchens up to level 5 are now fitted, joinery is progressing well, also up to level 5. Tiling following through, currently up to level 3. The top floor partition works are being completed, ready for plastering. Envelope final stages are being completed, the roofing is also fully installed.

Decorating is progressing well, working bottom up, currently up to the 2nd floor. Sanitary ware is being fitted on the 3rd floor along with 2nd fix joinery. Window frame 90% installed, external insulation and brick work also progressing.

Next panel

Next panel

Next panel

• ADELPHI WHARF PHASE 2 •

• LATEST UPDATE •

APRIL 2018.

Next panel

Next panel

Next panel

• ADELPHI WHARF PHASE 3 •

• LATEST UPDATE •

APRIL 2018. 

Building foundations have commenced followed by the main concrete frame for the blocks.

• DUE FOR COMPLETION 2018 •

Next panel

Next panel

Next panel

• GREEN QUARTER 7 •

• LATEST UPDATE •

APRIL 2018. 

Contiguous piling of the basement walls has commenced as planned.

• DUE FOR COMPLETION 2018 •

Next panel

Next panel

Next panel

• FORTIS QUAY •

• CONSTRUCTION ONSITE HAS COMMENCED •

APRIL 2018. 

Next panel

Next panel

Next panel

• SILKHOUSE COURT •

• LATEST UPDATE •

MARCH 2018. 

Wall partitions and insulation in now in place on all floors. Second fix is complete. Installation of glazing on upper floors is now in process. 

• DUE FOR COMPLETION Q2 2018 •

Next panel

Next panel

Next panel

• HALE ADDRESS •

• email •

• ALTRINCHAM ADDRESS •




FORTIS DEVELOPMENTS

BANK HOUSE

OLD MARKET PLACE

ALTRINCHAM

WA144PA

+44(0)161 974 5860

INFO@FORTISDEVELOPMENTS.COM

SUITE 4

RICHMOND HOUSE

HEATH ROAD

HALE

WA14 2XP

+44(0)161 974 5860